What the plan finds
The draft plan,
69 pages dated 30 June 2026, covers the council's buildings except its investment properties,
named as the Blue Haven Terralong retirement village, and the self-funded holiday parks.
There are 153 buildings (940 components)
with a gross replacement cost of $136 million as at 30 June, drawn from a draft 2026
revaluation by consultants (page 6).
On condition, the verdict is good news. Overall the assessed assets of Council owned buildings are in good condition
,
the plan says (page 33). By its dollar figures, $58.1 million of buildings are in excellent
condition, $72.6 million good, $4.3 million fair and $1.8 million poor, with none very poor.
There are no deferred renewals
,
no main building is past its useful life, and so
short-term condition-driven renewal pressure is very low
(page 35).
Building condition by replacement value
The plan's own grades and dollar values (page 33), its stated shares, and the shares those dollar values give.
| Condition | Value in the plan | Share the plan states | Share of $136.9m, our arithmetic |
|---|---|---|---|
| 1 Excellent | $58.1m | 50% | 42% |
| 2 Good | $72.6m | 42% | 53% |
| 3 Fair | $4.3m | 4% | 3% |
| 4 Poor | $1.8m | 4% | 1% |
| 5 Very poor | none | none | none |
The six components rated poor are two storerooms at Saddleback Mountain Reserve and four structures listed under the Kiama Gasworks: an office, an industrial shed, a two-storey structure with racking, and a shed. Together they would cost $1,844,150 to replace (table 14). The plan does not say what the council intends for them.
Where the money falls short
Over the ten years from 2026-27 to 2035-36, the plan puts the cost of looking after these
buildings at $62.9 million and the funding in the council's long-term financial plan at
$52.6 million. In its words,
the current funding model meets 83% of the costs required to maintain building assets
(page 7).
Ten years of building costs: what the plan says is needed, and what is budgeted
Maintenance and operations
- Needed, 2026-27 to 2035-36
- $32.5 million
- Budgeted
- $32.5 million
- Year one
- Funded at 100 per cent
Capital renewal
- Needed, 2026-27 to 2035-36
- $30.4 million
- Budgeted
- $20.1 million, about two-thirds
- Year one
- $1.9 million against $2.33 million needed, $428,500 short
The shortfall is all on the capital side. Maintenance is budgeted in full, so the money to keep buildings working day to day is there. What is short is the money to replace roofs, fittings and services as they wear out: the budget holds at about $2 million a year from 2031-32, while the plan's estimate of the need climbs, to $4.8 million in 2035-36 (table 1).
The plan's own test of this is the asset sustainability ratio, planned renewal spending
divided by annual depreciation. It comes out at 71 per cent against a benchmark of 100, which,
it says, means
Council is currently underinvesting in capital renewal expenditure relative to the rate of asset deterioration reflected through depreciation
(pages 6 and 53). Over time, the plan says, this is likely to mean more reliance on reactive
maintenance and higher whole-of-life costs.
What the council cannot yet measure
The plan is frank that some of its numbers rest on estimates.
whole-of-life costing cannot yet be accurately assessed due to gaps in current financial and asset management practices
It names two gaps (page 6):
The absence of structured income and expense accounts for Council-owned leased properties
,
and
The lack of an integrated work order system linking asset data with financial systems
.
It says the council is putting in the TechnologyOne work management system and tighter
budget controls for property. On data, the plan rates the building records as moderate
overall, but adds that
Data confidence in relation to asset lifecycle information in the Asset Register however is low
(page 51). The council's customer request system cannot yet track response times for building
work either, except for bookings of four public halls (page 23).
The same gap showed up in the council's
draft Strategic Asset Review,
which went to the 15 September meeting. It costed holding each property using a benchmark,
explaining:
As Council's current financial systems do not record maintenance costs for individual buildings and properties, maintenance costs have been estimated using recognised industry benchmarks
.
That review fed the council's decision on 20 October to endorse selling surplus and
non-strategic assets over three years. The buildings plan, written on its own track, says
There were no assets identified for decommissioning during the revaluation process
and that
no significant disposals are currently committed for this asset class
(pages 29 and 36). The draft asset review says it has focused primarily on Operational Land and road closure opportunities
,
so the two need not conflict. But if buildings are sold under that program, the buildings
plan's ten-year figures will need redoing.
How to comment, and what happens next
The council endorsed the draft for 28 days' exhibition on 20 October, as one of a group of items adopted together in one motion, nine votes to none (resolution 26/292OC, minutes pages 19 and 20). The staff report set a condition on what it would listen to:
As this plan is based on a model plan, feedback will only be considered if it strengthens the plan strategy.
The plan's path from here
- 20 October 2026Council endorses the draft for 28 days' public exhibition, 9 votes to 0.
- NowOn exhibition on the council's Your Say site, with an online form, email or post.
- 23 November 2026Submissions closed.
- After thatA further report to council if relevant submissions arrive or substantial changes are proposed. Otherwise the plan is adopted without one.
Resolution 26/292OC has the council
Adopt the Asset Management Plan – Buildings if there are no relevant submissions received and there are no substantial changes proposed for any other reasons
.
The Your Say page says
We invite you to review the draft and share your feedback by 23 November.
Submissions can go through the online form on that page, or by email or post. If the plan
comes back to council, or is adopted without a report, we will report which, and what changed.
Our read
This is opinion, built on the documents above. For a council under a state order to fix its finances, this is a reassuring document on the thing ratepayers can see: the halls, amenity blocks and leisure centre are, on a fresh consultant's assessment, in good shape, with nothing overdue. The pressure is a slow one. Two-thirds funding for renewal is manageable for a few years and expensive if it becomes a habit, and the plan says plainly that it is a habit now.
The staff report's condition, that feedback will count only if it strengthens the plan,
sets a narrow gate. The draft gives careful readers material that would pass it. Its figures
do not all agree: the financial summary on page 7 puts the capital need at $30.6 million
where its own table, page 35 and the opening summary say $30.4 million; page 33 puts poor-condition
assets at 4 per cent where page 35 says about 1 per cent, and the condition shares on page 33 do
not match its own dollar values (the table above). Its list of consequences of underfunding
on page 53 speaks of
Increase in risk to patrons and users of Recreation, Open Space and Other Structures assets
,
and several pages carry headers from that plan, which the council adopted last year. None of
that changes the headline finding, but a plan meant to guide ten years of spending should
have its numbers agree before it is adopted, and adoption without a further report depends on
nobody pointing that out.
How we sourced this
We read the 69-page draft plan in full, the staff report on item 16.1 in the 20 October agenda, resolution 26/292OC in the minutes, the council's Your Say pages for the plan, and the passage of the draft Strategic Asset Review quoted above. Page numbers are the plan's printed ones. The ten-year totals and ratios are the plan's; we recomputed them from its table 1: the total gap there comes to $10.29 million, which the plan rounds to $10.2 million, and the 83 per cent is $52.6 million over $62.9 million. The two-thirds capital share and the condition shares in the table are our arithmetic. The plan does not give addresses for the poor-condition assets, so we have not matched them to any site in the asset review. We have not contacted the council. The section headed Our read is opinion.
Sources
How we did it. AI did the heavy reading and the first draft; people own what it says. Built from the primary sources below. 18 quotations were machine-checked, character by character, against our archived copies. Read our method.
- Kiama Municipal Council, Draft Asset Management Plan: Buildings, dated 30 June 2026, 69 pages, read in full 5 November 2026: the scope and exclusions, 153 buildings and $136 million (pages 5 to 9), table 1 and the 83 per cent (page 7), customer requests (page 23), asset base growth and disposals (pages 29 and 36), condition and the poor assets (pages 33 and 34), renewals (pages 35 and 36), coastal study, data confidence (page 51), funding consequences and ratios (pages 53 and 54).
- Kiama Municipal Council, Your Say: Asset Management Plan: Buildings, read 5 November 2026: the 23 November closing date and how to make a submission.
- Kiama Municipal Council, Ordinary meeting 20 October 2026, agenda, item 16.1: the 28-day exhibition, the model plan and the condition on feedback.
- Kiama Municipal Council, Minutes of the ordinary meeting, 20 October 2026: the in globo resolution 26/273OC, resolution 26/292OC and its vote (pages 19 and 20), and resolution 26/296OC on divesting surplus and non-strategic assets over three years.
- Kiama Municipal Council, Draft Strategic Asset Review, for the 15 September 2026 meeting: how holding costs were estimated for buildings.
Spotted an error, or read these documents differently? Tell us and we will check it against the documents and log the outcome here.