What councillors decided

Item 15.3 at the 17 November meeting asked councillors to endorse planning proposal PP-2026-2417 and send it to the NSW Department of Planning, Housing and Infrastructure for a Gateway determination, the state’s first sign-off. The minutes record resolution 26/329OC, moved by Councillors Draisma and Larkins and carried with all nine councillors for and none against. As well as the Gateway request, the council resolved to seek authority to make the change itself as Local Plan Making Authority, to put new draft rules in the Kiama Development Control Plan 2020 on exhibition at the same time, and to receive a further report before anything is finalised.

What the map is

The state’s coastal planning policy, the Resilience and Hazards SEPP, has four kinds of coastal management area. The state mapped three of them itself. The fourth, the coastal vulnerability area, was left to councils, which the agenda report says were thought to have more accurate data and mapping for coastal hazards. Until a council supplies one, the SEPP’s rules for that area have no map to apply to.

Kiama’s map comes from its Kiama Coastline Coastal Management Program, which the planning proposal says the Minister certified on 23 September 2024. It covers land seaward of the program’s 2120 “unlikely” line: land that could be affected by a 1 per cent chance of coastal erosion by 2120, or a 5 per cent chance of tidal or coastal inundation. Despite the name, this is the generous line, not the tight one. The proposal says the figures represent the upper limits for erosion and inundation estimates in approximately 100 years.

Kiama council's map of the proposed Coastal Vulnerability Area: a red band along the coast from Minnamurra in the north, past Kiama Downs, Bombo, Kiama, Kiama Heights, Werri Beach and Gerringong, to Gerroa and the beach south of it to the Shoalhaven boundary, widest at Bombo, around Kiama and at Gerroa
The proposed Coastal Vulnerability Area, shaded red, from Kiama Municipal Council’s 17 November 2026 enclosures (PDF page 526). Fourteen street-scale detail maps follow on PDF pages 527 to 540; that file is 165 MB.

The overview map shows a band along almost the whole coast. On our reading of it, the band is a thin strip along most headlands and beaches and widens at Bombo, around Kiama town and at Gerroa, from where it runs along the beach to the Shoalhaven boundary, which the proposal puts 2km south of Black Head.

What would change if you build inside it

The planning proposal itself does not rezone land and, it says, will not create additional development opportunities or prohibit development. What changes is the paperwork and the test. The draft development control plan chapter, Topic 2.6, says a development application inside the area must come with a Coastal Risk Management Report written by a coastal or structural engineer, who must be named with their qualifications. A

Exhibit A · from the source

Kiama council enclosures, 17 November 2026, PDF page 542: draft control that development applications in the Coastal Vulnerability Area must be accompanied by a Coastal Risk Management Report prepared by a coastal and/or structural engineer
PDF page 542 of Kiama Municipal Council’s 17 November 2026 enclosures, item 15.3, enclosure 4: the draft Kiama DCP 2020 Topic 2.6. Outlined: the report requirement and who must write it. Open the PDF at page 542 Back to the story

The report must place the development against the 2120 line, identify the current and projected hazards other than coastal inundation, assess how an eroding escarpment would weaken foundations, recommend foundation design and protection works, and set out how occupants and property would be protected from a 1 per cent annual chance event over the building’s life. Approved coastline protection structures that are kept must be certified as able to withstand that event.

There are carve-outs. The council may waive the report for some buildings and works on residential land, and it is not required for structures on residential land with a short design life, likely to be replaced before 2040, or that can be easily moved. Further out, on land seaward of the program’s 2120 “almost certain” line, the draft says Council is unlikely to support development proposals for buildings or works, apart from things that need to be at the water, such as boat ramps, jetties, surf lifesaving and marine rescue facilities and coastal protection works.

What it costs, in the council's words

The council’s report says there is no cost to the council in lodging the proposal, which is paid for by a grant. For landowners the planning proposal is candid: Some of these factors can increase the cost of development by increasing the information the applicant needs to compile and by impacting on the location, design and construction of the development. It adds that These costs reflect the nature of the hazard and are reasonable, and argues that resilient building now spares future generations the pressure for major public expenditure that badly placed development would create. The agenda report warns that without the map the SEPP change cannot proceed, which will impact the safety of existing and future residents and development in the area.

Neither document says how many lots or homes sit inside the line, and neither puts a figure on what a Coastal Risk Management Report costs.

What happens next, and when you can comment

The planning proposal’s timeline, which it calls a target, runs like this:

  • December 2026: submitted to the department.
  • January to February 2027: Gateway determination.
  • March 2027: state agency consultation, then public exhibition. The proposal suggests 28 days, on the NSW Planning Portal with a link from the council’s Your Say site, and notification letters to affected landowners. The draft development control plan chapter would be on exhibition at the same time.
  • June to July 2027: back to council for final endorsement.
  • August 2027: the anticipated date the SEPP amendment is published.

The department’s Gateway determination can change the exhibition length and add conditions. When the Gateway determination is issued or the exhibition opens, we will report its dates and any conditions it sets.

Our read

This is opinion, built on the documents above.

This is the right thing to do, and it is late. The state issued guidance for these maps in August 2020, and Kiama’s coastal management program was certified more than two years ago. Until the map is in the SEPP, the state’s own rules for building on vulnerable coastal land have nothing to bite on in Kiama. A clear line, drawn from the council’s own modelling, is fairer to owners than case-by-case argument.

But the exhibition needs to answer the question owners will ask first. The papers say there will be socio-economic effects and extra costs, and do not say how many properties are inside the line or roughly what the engineer’s report costs. A 14-page set of detail maps inside a 165 MB PDF is not a way for a resident to check their own block. When this goes on exhibition, the council should publish a count of affected lots and an address search, and the letters should go out when it opens. The “unlikely” label will also mislead some readers into thinking the risk is remote; it is the outer edge of a 100-year projection, and the exhibition material should say so in plain words.

How we sourced this

We read item 15.3 of the 17 November 2026 agenda in full (PDF pages 122 to 129), the planning proposal report (enclosure 1, PDF pages 507 to 525) and the draft development control plan amendments (enclosure 4, PDF pages 541 to 544) in the meeting enclosures, and resolution 26/329OC in the published minutes (PDF page 15). We looked at the overview map (PDF page 526) and several detail maps; our description of where the band is wide or thin is our reading of that map, not a measurement, and we have not checked any individual property. The planning proposal’s page stamps run one behind the PDF page numbers; we cite PDF pages. The development control plan chapter is a draft and the map is not yet in force. We have not contacted the council. The section headed Our read is opinion.

Sources

How we did it. AI did the heavy reading and the first draft; people own what it says. Built from the primary sources below. 7 quotations were machine-checked, character by character, against our archived copies. Read our method.

  1. Kiama Municipal Council, Ordinary meeting 17 November 2026, minutes (26 pages), read 21 November 2026: item 15.3, resolution 26/329OC and the vote (PDF page 15).
  2. Kiama Municipal Council, Ordinary meeting 17 November 2026, agenda (176 pages), read 21 November 2026: item 15.3, Endorse for Gateway: Planning Proposal PP-2026-2417, Coastal Vulnerability Area (PDF pages 122 to 129).
  3. Kiama Municipal Council, Ordinary meeting 17 November 2026, enclosures (725 pages), read 21 November 2026: item 15.3 enclosures 1 to 4, the planning proposal report (PDF pages 507 to 525), overview and detail maps (PDF pages 526 to 540) and draft Kiama DCP 2020 Topic 2.6 (PDF pages 541 to 544). Shown in Exhibit A.

Spotted an error, or read these documents differently? Tell us and we will check it against the documents and log the outcome here.